Question: Activity Predecessor Regular Time Time When Fully Crashed Regular Cost Cost When Fully Crashed A S 3 1 100 200 B T 2 1 25
Activity Predecessor Regular Time Time When Fully Crashed Regular Cost Cost When Fully Crashed A S 3 1 100 200 B T 2 1 25 75 D A 2 1 50 100 M U 2 1 100 400 O B 2 1 75 150 P D, M, Y 5 2 500 2000 R T 4 2 200 300 S T 1 1 T 5 4 100 700 U R 1 1 Y O 1 1
Consider the following information for this project:
a. What is the critical path and expected time?
b. How much would it cost to crash the time by 1 day?
c. How much would it cost to crash the time by 2 days?
d. By the maximum you can possibly crash?