Question: Activity Predecessor Regular Time Time When Fully Crashed Regular Cost Cost When Fully Crashed A S 3 1 100 200 B T 2 1 25

Activity Predecessor Regular Time Time When Fully Crashed Regular Cost Cost When Fully Crashed
A S 3 1 100 200
B T 2 1 25 75
D A 2 1 50 100
M U 2 1 100 400
O B 2 1 75 150
P D, M, Y 5 2 500 2000
R T 4 2 200 300
S T 1 1
T 5 4 100 700
U R 1 1
Y O 1 1

Consider the following information for this project:

a. What is the critical path and expected time?

b. How much would it cost to crash the time by 1 day?

c. How much would it cost to crash the time by 2 days?

d. By the maximum you can possibly crash?