Question: Activity Predecessor | Time (days) Time Time (days) t Optimistic (days) Pessimistic Most likely a 15 18 25 15 18 20 C ab 6 10

Activity Predecessor | Time (days) Time Time
Activity Predecessor | Time (days) Time Time (days) t Optimistic (days) Pessimistic Most likely a 15 18 25 15 18 20 C ab 6 10 12 O C 18 24 26 13 19 25 O 12 18 23 O 15 17 19 n 1.g 22 25 30 e.1 11 15 17 4.1 Calculate the time (t) and variance (v) for each activity. (8) 4.2 Describe how the network diagram (AON) can be used for the information presented above. (diagram not required) (12) 4.3 Identify the paths and the critical path.