Question: Activity Predecessor Time ( weeks ) A - - 6 B - - 6 C A 4 D B 9 E C , D 1
Activity Predecessor Timeweeks
A
B
C A
D B
E CD
F E
Using Table what is the largest amount of slack that any activity in the project has?
Question Select one:
A
two weeks
B
zero weeks
C
five weeks
D
four weeks
G D E
H E
I E F
J G H I
K H I
L I
Using Table suppose activity D can be shortened from four days to one day. Assume all other activity times remain the same. How much shorter will the total project earliest completion time become?
Question Select one:
A
one day
B
zero days
C
three days
D
two days