Question: Activity Predecessor Time ( weeks ) A - - 6 B - - 6 C A 4 D B 9 E C , D 1

Activity Predecessor Time(weeks)
A --6
B --6
C A 4
D B 9
E C,D 11
F E 3
Using Table 7.4, what is the largest amount of slack that any activity in the project has?
Question 4Select one:
A.
two weeks
B.
zero weeks
C.
five weeks
D.
four weeks
G D, E 1
H E 6
I E, F 2
J G, H, I 4
K H, I 3
L I 6
Using Table 7.6, suppose activity D can be shortened from four days to one day. Assume all other activity times remain the same. How much shorter will the total project earliest completion time become?
Question 3Select one:
A.
one day
B.
zero days
C.
three days
D.
two days

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!