Question: Activity Predecessor(s) A Duration (days) B 15 A C 20 A D 15 A F 15 B. C F 60 D G 15 E H

 Activity Predecessor(s) A Duration (days) B 15 A C 20 A

Activity Predecessor(s) A Duration (days) B 15 A C 20 A D 15 A F 15 B. C F 60 D G 15 E H 20 E 15 F, G, H 2 activity F? Consider the network scheduling data presented in the table above. How many days of slack are associate