Question: The following represents a project that should be scheduled using CPM Immediate Time (Days) Activity predecessors a m b ET 2 A - 1 3
| The following represents a project that should be scheduled using CPM | |||||||
| Immediate | Time (Days) | ||||||
| Activity | predecessors | a | m | b | ET | 2 | |
| A | - | 1 | 3 | 6 | |||
| B | - | 1 | 2 | 4 | |||
| C | A | 1 | 2 | 3 | |||
| D | A | 2 | 3 | 4 | |||
| E | B | 3 | 4 | 10 | |||
| F | C, D | 3 | 4 | 5 | |||
| G | D, E | 1 | 4 | 7 | |||
| H | F, G | 2 | 4 | 5 | |||
| a. Complete the table | |||||||
| b. Draw the Network Diagram | |||||||
| c. What is the critical path? | ||||||
| d. What is the expected project completion time?' | ||||||
| e. What is the probability of completing this project within 16 days? | ||||||
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock