Question: Activity Predecessors Duration a none 3 b none 6 c none 8 d a 7 e b 5 f c 1 0 g c 4
Activity Predecessors Duration
a none
b none
c none
d a
e b
f c
g c
h def
i g
What is the EF for activity h
Wrong
What is the LF for activity i
Wrong