Question: Activity Predecessors Duration a none 3 b none 6 c none 8 d a 7 e b 5 f c 1 0 g c 4

Activity Predecessors Duration
a none 3
b none 6
c none 8
d a 7
e b 5
f c 10
g c 4
h d,e,f 5
i g 6
19 What is the EF for activity h?
8
12
13
18(Wrong)
23
20. What is the LF for activity i?
8
12
13
18(Wrong)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!