Question: Activity Predecessors Durations (days) A none 2 B A 3 . 4 D B 1 1 E B and C 3 F D and E

Activity Predecessors Durations (days) A none 2 B
Activity Predecessors Durations (days) A none 2 B A 3 . 4 D B 1 1 E B and C 3 F D and E 6 G C and D 3 For the project above, the earliest start for activity D is: Seleccione una: a. 4 b. 8 O c. 5 O d. 6