Question: Activity Predecessors Durations (days) A none 2 B A 3 C A 4 D B 1 E B and C 3 F D and E
| Activity | Predecessors | Durations (days) |
| A | none | 2 |
| B | A | 3 |
| C | A | 4 |
| D | B | 1 |
| E | B and C | 3 |
| F | D and E | 6 |
| G | C and D | 3 |
For the preceding project, the latest finish for activity G is:
Select one:
a. 16
b. 9
c. 15
d. 12
Clear my choice
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts