Question: Activity Predecessors Durations (days) A none 2 B A 3 C A 4 D B 1 E B and C 3 F D and E

Activity

Predecessors

Durations (days)

A

none

2

B

A

3

C

A

4

D

B

1

E

B and C

3

F

D and E

6

G

C and D

3

For the preceding project, the latest finish for activity G is:

Select one:

a. 16

b. 9

c. 15

d. 12