Question: Activity Predessor Duration A 7 B 6 C 33 D B 24 E C 4.1 F D 9 G A,B 12 H E 10 I
| Activity | Predessor | Duration | |
| A |
| ||
| B | 6 | ||
| C | 33 | ||
| D | B | 24 | |
| E | C | 4.1 | |
| F | D | 9 | |
| G | A,B | 12 | |
| H | E | 10 | |
| I | G | 7 | |
| J | F,G | 10 |
Use the information above and draw a network diagram showing the L/S, E/S, E/F, L/F, Slack, and Critical Path