Question: Activity Predessor Duration A 7 B 6 C 33 D B 24 E C 4.1 F D 9 G A,B 12 H E 10 I

Activity Predessor Duration
A

7
B 6
C 33
D B 24
E C 4.1
F D 9
G A,B 12
H E 10
I G 7
J F,G 10

Use the information above and draw a network diagram showing the L/S, E/S, E/F, L/F, Slack, and Critical Path