Question: Given the information below: Activity Immediate Predecessors Duration (days) A - 5 B - 6 C - 3 D C 2 E A 5 F

Given the information below:

Activity Immediate Predecessors Duration (days)
A - 5
B - 6
C - 3
D C 2
E A 5
F B, D 10
G C 7

  1. This project will be completed in days.
  2. Is task A critical?(type yes or no):
  3. Task B has a total float of days.