Question: Given the information below: Activity Immediate Predecessors Duration (days) A - 5 B - 6 C - 3 D C 2 E A 5 F
Given the information below:
| Activity | Immediate Predecessors | Duration (days) |
|---|---|---|
| A | - | 5 |
| B | - | 6 |
| C | - | 3 |
| D | C | 2 |
| E | A | 5 |
| F | B, D | 10 |
| G | C | 7 |
- This project will be completed in days.
- Is task A critical?(type yes or no):
- Task B has a total float of days.