Question: Activity Previous Activity Normal time Shortened time Normal cost Shortened cost A - 3 2 1000 1600 B - 2 1 2000 2700 C -
| Activity | Previous Activity | Normal time | Shortened time | Normal cost | Shortened cost |
| A | - | 3 | 2 | 1000 | 1600 |
| B | - | 2 | 1 | 2000 | 2700 |
| C | - | 1 | 1 | 300 | 300 |
| D | A | 7 | 3 | 1300 | 1600 |
| E | B | 6 | 3 | 850 | 1000 |
| F | C | 2 | 1 | 4000 | 5000 |
| G | D,E | 4 | 2 | 1500 | 2000 |
- Identify the critical path and the project implementation period?
- How much will be the cost of reducing the project period to the shortest possible period?
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts