Question: Activity Q duration = 6 Activity M duration = 8 Activity R duration = 6 Consider the activity nodes depicted above and assume you are

Activity Q duration =6
Activity M duration =8
Activity R duration =6
Consider the activity nodes depicted above and assume you are making a forward pass through this project network. If the Early Finish (EF) time for activity Q is 22, and the Early Finish (EF) time for activity M is 24, what is the Early Start (ES) time for activity R?
Group of answer choices
20
28
26
24

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!