Question: ACTIVITY SLACK NORMAL TIME CRASH TIME NORMAL COST CRASH COST J 1 7 6 $ 80,000 $ 120,000 K 1 6 4 $ 200,000 $
ACTIVITY SLACK NORMAL TIME CRASH TIME NORMAL COST CRASH COST J 1 7 6 $ 80,000 $ 120,000 K 1 6 4 $ 200,000 $ 320,000 L 3 3 2 $ 90,000 $ 100,000 M 3 2 1 $ 180,000 $ 250,000 N 0 4 2 $ 225,000 $ 450,000 P 0 3 2 $ 100,000 $ 150,000 Q 1 4 2 $ 310,000 $ 500,000 R 0 2 2 $ 400,000 $ 400,000 If you needed to crash this project by one week, activity P is the
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts