Question: Activity Slack Time Activity ES EF LS LF Slack A 0 3 0 0 B 3 5.5 0 0 C 5.5 9.5 0 0 D
Activity Slack Time
Activity ES EF LS LF Slack
A 0 3 0 0
B 3 5.5 0 0
C 5.5 9.5 0 0
D 9.5 13 0 0
E 13 14 0 0
Determining the Critical Path
A critical path is a path of activities, from the Start node to the Finish node, with 0 slack times.
Critical Path:
The project completion time equals the sum of the duration times of all activities along the critical path.
Project Completion Time: