Question: activity prec act t es ef ls lf slack critical A -- 5 0 5 B -- 4 0 4 C -- 8 0 8
| activity | prec act | t | es | ef | ls | lf | slack | critical |
| A | -- | 5 | 0 | 5 | ||||
| B | -- | 4 | 0 | 4 | ||||
| C | -- | 8 | 0 | 8 | ||||
| D | A, B | 4 | 5 | 9 | 18 | 22 | ||
| E | C | 12 | 9 | 17 | ||||
| F | C | 10 | 9 | 18 | ||||
| G | D, E | 3 | 21 | 20 | ||||
| H | E | 2 | 21 | 19 | ||||
| I | E, F | 5 | 17 | 23 |