Question: ACTIVITY START DATE FINISH DATE RESOURCE PER DAY J 1 2 4 K 3 4 2 L 3 4 3 M 5 6 2 N
ACTIVITY START DATE FINISH DATE RESOURCE PER DAY J 1 2 4 K 3 4 2 L 3 4 3 M 5 6 2 N 7 10 1 O 11 11 2 3.1 Construct a Gantts chart assuming all activities begin as early as possible and show the resource loading profile. (10 marks) 3.2 Choose the most appropriate option and improve the resource loading profile. (6 marks) 3.3 Construct a resource histogram reflecting the improved loading profile