Question: Activity Time Estimates (Weeks) Predecessor Activity B. Build Facility F. Safety Inspection C. Install Equipment None B B D. Recruit Workers None E.Train Workers D

Activity Time Estimates (Weeks) Predecessor
Activity Time Estimates (Weeks) Predecessor Activity B. Build Facility F. Safety Inspection C. Install Equipment None B B D. Recruit Workers None E.Train Workers D A. Perform Pilot C,E,F The sequencing, predecessor activities, and time estimates of a construction project are seen on the table above. Please draw the PERT diagram, find critical path and answer the following questions. What is the critical path? Write the Project completion time. What is the probability to finish the project on time