Question: Activity Time Estimates (Weeks) Predecessor Activity B. Build Facility None F. Safety Inspection C. Install Equipment D. Recruit Workers E.Train Workers None D A. Perform

Activity Time Estimates (Weeks) Predecessor
Activity Time Estimates (Weeks) Predecessor Activity B. Build Facility None F. Safety Inspection C. Install Equipment D. Recruit Workers E.Train Workers None D A. Perform Pilot C.E.F The sequencing, predecessor activities, and time estimates of a construction project are seen on the table above. Please draw the PERT diagram, find critical path and answer the following questions. What is the critical path? Write the Project completion time. What is the probability to finish the project on time

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!