activity times:
\table[[Activity,Time (weeks),Immediate Predecessor(s),Activity,Time (weeks),Immediate Predecessor(s)],[A,5,-,E,4,B],[B,7,-,F,5,B],[C,3,A,G,11,C, E],[D,1,A,H,6,D, F]]
Dave's earliest start (ES) and earliest finish (EF) are:
\table[[Activity,ES,EF],[A,,5],[B,0,],[C,,8],[D,5,],[E,,11],[F,7,],[G,,22],[H,,18]]
Dave's latest start (LS) and latest finish (LF) are:
\table[[Activity,LS,LF],[H,16,],[G,11,],[F,11,],[E,7,],[D,15,],[C,8,],[B,0,],[A,3,]]
 activity times: \table[[Activity,Time (weeks),Immediate Predecessor(s),Activity,Time (weeks),Immediate Predecessor(s)],[A,5,-,E,4,B],[B,7,-,F,5,B],[C,3,A,G,11,C, E],[D,1,A,H,6,D, F]] Dave's earliest

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!