Question: Activy Activ Figure 2. Selected Nodes in a Network Consider the activity nodes depicted in Figure 2 and assume you are making a forward pass

Activy Activ Figure 2. Selected Nodes in a
Activy Activ Figure 2. Selected Nodes in a Network Consider the activity nodes depicted in Figure 2 and assume you are making a forward pass through this project network. If the Early Finish (EF) time for activity Q is 26, and the Early Finish (EF) time for activity M is 28, what is the Early Start (ES) time for activity R? O a. 26 b.24 C. 20 O d. 28