Question: a-d please a m Time Estimates Immediate b Activity Predecessor(s) optimistic) (most likely) (pessimistic) A 1 3 8 B 7 7 19 A 2 4
a-d please
a m Time Estimates Immediate b Activity Predecessor(s) optimistic) (most likely) (pessimistic) A 1 3 8 B 7 7 19 A 2 4 6 D BC 3 5 E C 3 4 5 F D, E 4 6 0 - 00 8 (a) Compute (2 pts) the expected duration of each activity and (2 pts) the variance of the duration of each activity. Round your answers to two decimal places. Activity Expected Time Variance A B D E F (b) (1 PT] Draw the activity-on-node network. (c) 2 PTS] Identify the critical path. (d) (2 PTS) Compute the expected project completion time. Round your answer to one decimal place Step by Step Solution