Question: a)Draw critical path analysis b)Identify and explain any non-critical tasks and the float (free slack) on each c)Duration of the project Activity Duration (Days) Predescessor
a)Draw critical path analysis
b)Identify and explain any non-critical tasks and the float (free slack) on each
c)Duration of the project
| Activity | Duration (Days) | Predescessor |
| A | 4 | - |
| B | 3 | A |
| C | 4 | A |
| D | 5 | - |
| E | 4 | D |
| F | 3 | B,C,D |
| G | 4 | F |
| H | 6 | E |
| I | 2 | G,H |
Step by Step Solution
3.47 Rating (154 Votes )
There are 3 Steps involved in it
a The critical path network diagram is as below Possible paths are ABFGI 43342 16 ACFGI 44342 17 DFG... View full answer