Question: Advantage Energy Technology Data Center Migration (DCM) Given DCM story, the budget, and the schedule details below, follow the Risk Management Process steps outlined in
Advantage Energy Technology Data Center Migration (DCM)
Given DCM story, the budget, and the schedule details below, follow the Risk Management Process steps outlined in Figure 7.2
Step 1: Identify a minimum of five risks to the DCM project.
Step 2: Use the Impact Scale in Figure 7.5 (or create your own scale) and plot the risks on a Risk Severity Matrix (like Figure 7.7).
Step 3: Develop a Risk Response Matrix (like Figure 7.8).
Step 4: Create a simple Change Request Form (like Figure 7.10).
DCM Project Budget...
Total Budget = $85,000
Initial design Work = 10%
Ventilation System = 35% (Parts = 20%; labor = 15%)
New Racks = 20% (Parts = 15%; labor = 5%)
Power Supplies and Cables = 25% (Parts = 15%; labor = 10%)
Switchover Ops Checks = 10%


Figures...





\begin{tabular}{|c|} \hline Total Budget \\ $85,000 \\ \hline \end{tabular} \begin{tabular}{|c|c|} \hline Design \\ $8,500 \\ $29,750 \\ Ventilation \\ Parts = \\ $17,000 \\ Labor = \\ $12,750 \end{tabular} \begin{tabular}{|c|c|} \hline Racks & Power$17,000Supplies&Cables \\ $21,250Parts=$12,750Labor=$4,250 & Parts=$12,750Labor=$8,500 \\ \hline \end{tabular} CP=2,4,10,15,16,17,18,19Projectduration=86.16days FIGURE 7.2 The Risk Management Process Documentation of scenario analyses can be seen in various risk assessment forms used by companies. Figure 7.6 is a partial example of a risk assessment form d on an information systems project involving an operating systems (OS) upgrade. Yellow zone (moderate risk) Green zone (minor risk) FIGURE 7.8 Risk Response Matrix FIGURE 7.10 Sample Change Request Description of requested change 1. Request river dancers to replace small Irish dance group. 2. Request one combination dance with river dancers and China ballet group. Reason for change River dancers will enhance stature of event. The group is well known and loved by Chinese people. Areas of impact of proposed change-describe each on separate sheet Scope Cost Other Schedule Risk \begin{tabular}{|c|} \hline Total Budget \\ $85,000 \\ \hline \end{tabular} \begin{tabular}{|c|c|} \hline Design \\ $8,500 \\ $29,750 \\ Ventilation \\ Parts = \\ $17,000 \\ Labor = \\ $12,750 \end{tabular} \begin{tabular}{|c|c|} \hline Racks & Power$17,000Supplies&Cables \\ $21,250Parts=$12,750Labor=$4,250 & Parts=$12,750Labor=$8,500 \\ \hline \end{tabular} CP=2,4,10,15,16,17,18,19Projectduration=86.16days FIGURE 7.2 The Risk Management Process Documentation of scenario analyses can be seen in various risk assessment forms used by companies. Figure 7.6 is a partial example of a risk assessment form d on an information systems project involving an operating systems (OS) upgrade. Yellow zone (moderate risk) Green zone (minor risk) FIGURE 7.8 Risk Response Matrix FIGURE 7.10 Sample Change Request Description of requested change 1. Request river dancers to replace small Irish dance group. 2. Request one combination dance with river dancers and China ballet group. Reason for change River dancers will enhance stature of event. The group is well known and loved by Chinese people. Areas of impact of proposed change-describe each on separate sheet Scope Cost Other Schedule Risk
Step by Step Solution
There are 3 Steps involved in it
To complete the assignment for the Advantage Energy Techno... View full answer