Question: a-e please I will rate! 5- Consider the following example of a three-step process. Assuming the demand is unlimited. (15 points) The first step takes
a-e please I will rate!
5- Consider the following example of a three-step process. Assuming the demand is unlimited. (15 points) The first step takes 25 minutes/unit. The second step takes 12 minutes/unit. The third step takes 15 minutes/unit. a- What is the total idle time of the process, assuming unlimited demand? b- What is the cycle time of the process? c- What is the utilization of the process? d- What would be the idle time if the first step takes 14 minutes/unit? e- What is the utilization of the process if the first step take 14 minutes/unit