Question: a)Fill in the network diagram below Task Time (wk) Predecessor Min Time with Crashing Crashing cost/wk ES EF LS LF Slack Critical (Y/N) Free Slack

a)Fill in the network diagram below

Task

Time (wk)

Predecessor

Min Time with Crashing

Crashing cost/wk

ES

EF

LS

LF

Slack

Critical (Y/N)

Free Slack

A

5

-

4

$50

B

3

-

2

$10

C

6

A

3

$2,500

D

3

A

1

$10

E

8

C,B

7

$200

F

3

D,E

1

$1,000

G

4

F

4

-

Task

Time (wk)

Predecessor

Min Time with Crashing

Crashing cost/wk

ES

EF

LS

LF

Slack

Critical (Y/N)

Free Slack

A

5

-

4

$50

B

3

-

2

$10

C

6

A

3

$2,500

D

3

A

1

$10

E

8

C,B

7

$200

F

3

D,E

1

$1,000

G

4

F

4

-

b-Clearly List your critical path

c-What is the shortest time need to complete the project (without expediting)?

d-To expedite the project by two weeks, which activities will you crash? Crashing cost?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!