Question: a)Fill in the network diagram below Task Time (wk) Predecessor Min Time with Crashing Crashing cost/wk ES EF LS LF Slack Critical (Y/N) Free Slack
a)Fill in the network diagram below
| Task | Time (wk) | Predecessor | Min Time with Crashing | Crashing cost/wk | ES | EF | LS | LF | Slack | Critical (Y/N) | Free Slack |
| A | 5 | - | 4 | $50 |
|
|
|
|
|
|
|
| B | 3 | - | 2 | $10 |
|
|
|
|
|
|
|
| C | 6 | A | 3 | $2,500 |
|
|
|
|
|
|
|
| D | 3 | A | 1 | $10 |
|
|
|
|
|
|
|
| E | 8 | C,B | 7 | $200 |
|
|
|
|
|
|
|
| F | 3 | D,E | 1 | $1,000 |
|
|
|
|
|
|
|
| G | 4 | F | 4 | - |
|
|
|
|
|
|
|
| Task | Time (wk) | Predecessor | Min Time with Crashing | Crashing cost/wk | ES | EF | LS | LF | Slack | Critical (Y/N) | Free Slack |
| A | 5 | - | 4 | $50 |
|
|
|
|
|
|
|
| B | 3 | - | 2 | $10 |
|
|
|
|
|
|
|
| C | 6 | A | 3 | $2,500 |
|
|
|
|
|
|
|
| D | 3 | A | 1 | $10 |
|
|
|
|
|
|
|
| E | 8 | C,B | 7 | $200 |
|
|
|
|
|
|
|
| F | 3 | D,E | 1 | $1,000 |
|
|
|
|
|
|
|
| G | 4 | F | 4 | - |
|
|
|
|
|
|
|
b-Clearly List your critical path
c-What is the shortest time need to complete the project (without expediting)?
d-To expedite the project by two weeks, which activities will you crash? Crashing cost?