Question: After creating a WBS and a network diagram for her project, Abdul calculated three different work paths. JBDL = 11 days ADEC = 8 days

After creating a WBS and a network diagram for

After creating a WBS and a network diagram for her project, Abdul calculated three different work paths. JBDL = 11 days ADEC = 8 days AJDG = 7 days The critical path of this network is The slack time for activity D in days is The slack time for activity A in days is