Question: After creating a WBS and a network diagram for her project, Lin calculated three different work paths. ABC = 10 days ADE = 12 days

After creating a WBS and a network diagram for her project, Lin calculated three different work paths.

ABC = 10 days

ADE = 12 days

BFG = 9 days

The critical path of this network is _____

The slack time for activity B in days is _____

The slack time for activity F in days is _____