Question: After creating a WBS and a network diagram for her project, Lin calculated three different work paths. ABC = 10 days ADE = 12 days
After creating a WBS and a network diagram for her project, Lin calculated three different work paths.
ABC = 10 days
ADE = 12 days
BFG = 9 days
The critical path of this network is _____
The slack time for activity B in days is _____
The slack time for activity F in days is _____