Question: After creating a WBS and a network diagram for her project, Lin calculated three different work paths. ABC = 10 days ADE = 12 days

  1. After creating a WBS and a network diagram for her project, Lin calculated three different work paths.

    ABC = 10 days

    ADE = 12 days

    BFG = 9 days

    The critical path of this network is

    The slack time for activity B in days is

    The slack time for activity F in days is

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!