Question: After defining project scope, an event coordinator can use a project plan that specifies the structure and scheduling of the tasks required to deliver the

After defining project scope, an event coordinator can use a project plan that specifies the structure and scheduling of the tasks required to deliver the event. Which is NOT a main output (project plan) of the scope definition?
Activity Sequencing
Activity Scheduling
Work Breakdown Structure
Operations Plan