Question: After developing the initial project schedule, you find that the customer delivery date cannot be met even if you put on additional resources. You determine
After developing the initial project schedule, you find that the customer delivery date cannot be met even if you put on additional resources. You determine that the only way to achieve this is to incorporate 2 weeks lead of coding and 3 weeks lead for testing, though it is not ideal to commence coding before the design is complete and commence testing before coding is complete. Your team has assured you that they will be able to manage the risk. This is an example of