Question: After noticing machine malfunction on the manufacturing floor, Lars immediately halts production as he realizes production is not up to standard. This delays delivery by
After noticing machine malfunction on the manufacturing floor, Lars immediately halts production as he realizes production is not up to standard. This delays delivery by two days till the machine is repaired, but he is rewarded for his actions as it prevented a faulty prototype from being developed. This is an example ofwhat
a Onedimensional control, as it pertains to control of manufacturing b Preventive control, which seeks to address future problems before they occur c onedimensional control as it is a specine issue d preventive control, rather than reactive repair work which is expensive
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock