Question: After preparing the project management plan, a project manager schedules a meeting with key stakeholders to finalize the planning phase. The project manager is now

After preparing the project management plan, a project manager schedules a meeting with key stakeholders to finalize the planning phase. The project manager is now preparing for the executing phase.
What should the project manager do next?
A.Define the project and create the project charter.
B.Put the project plan into action.
C.Ensure all deliverables are completed.
D.Address risks to make sure the project is on track.