Question: Aggregate Planning In-class Exercise Each worker can produce 200 units per quarter Cost to hire a worker $300/worker Cost to layoff a worker $200/worker Inventory
Aggregate Planning In-class Exercise
-
Each worker can produce 200 units per quarter
-
Cost to hire a worker $300/worker
-
Cost to layoff a worker $200/worker
-
Inventory holding cost $1/unit/Qtr
-
Backlog holding cost $3/unit/Qtr
QTR Demand
1 : 4000
2 : 6000
3 : 9000
4 : 5000
Current Inventory = 0 units
Current Backlog = 0 units
Current # of workers = 30
All demand must be met by the end of the planning horizon
Try to develop an aggregate production plan for this example that minimizes total costs.