Question: Al Fanateer IT hardware project was completed within scope, time and cost goals. However, the project sponsor was not satisfied with the product delivered and

Al Fanateer IT hardware project was completed within scope, time and cost goals. However, the project sponsor was not satisfied with the product delivered and said it is not up to his expectations. Which of the following statements is true?

A.

The project is failure based on the triple constraints

B.

The project is failure according to sponsor expectations

C.

The project is success according to the quadruple constraints

D.

All above statements are true