Question: All times are in weeks. What is the minimum expected completion time for the project? Explain answer. Activity Immediate Predecessor Optimistic Time Most Likely Time
All times are in weeks. What is the minimum expected completion time for the project? Explain answer.
| Activity | Immediate Predecessor | Optimistic Time | Most Likely Time | Pessimistic Time |
| A | -- | 2 | 10 | 14 |
| B | -- | 8 | 8 | 8 |
| C | A | 6 | 9 | 18 |
| D | B | 5 | 11 | 17 |
Step by Step Solution