Question: An accepted deadline for a project schedule approaches. However, the project manager realizes only 90% percent of the work has been completed. The project manager
An accepted deadline for a project schedule approaches. However, the project manager realizes only 90% percent of the work has been completed. The project manager then issues a change request. Identify the change request authorize to handle this situation?
A. Additional resources using the contingency fund
B. Escalation approval to use contingency funding
C. Corrective action based on causes
D. Team overtime to meet schedule