Question: An activity, A , has two succeeding activities, B and C . Given the following information, determine the latest starting time for activity A .

An activity, A, has two succeeding activities, B and C. Given the following information, determine the latest starting time for activity A.
EFB=15,EFC=17, LF B=24,LFC=27; activity times are A=4,B=6,C=8.
Select one:
a.14
b.15
c.16
d.17
e.18