Question: An activity, A, has two succeeding activities, B and C. Given the following information, determine the latest starting time for activity A. EF B =

An activity, A, has two succeeding activities, B
An activity, A, has two succeeding activities, B and C. Given the following information, determine the latest starting time for activity A. EF B = 15, EF C = 17, LF B = 24, LF C = 27; activity times are A = 4, B = 6, C = 8. a. 17 b. 14 C. 18 d. 15 e. 16