Question: An activity, A , has two succeeding activities, B and C . Given the following information, determine the latest starting time for activity A .

An activity, A, has two succeeding activities, B and C. Given the following information, determine the latest starting time for activity A.
EF B =15, EF C =17, LF B =24, LF C =27; activity times are A =4, B =6, C =8.