Question: An activity of a project has 2 immediate predecessors, whose EF's are 32and 14, respectively. What is the ES of the activity? Enter a whole

An activity of a project has 2 immediate predecessors, whose EF's are 32and 14, respectively. What is the ES of the activity? Enter a whole number