Question: Enter the Immediate Predecessors information into cells B4-B11 Compute and enter the ES, EF, LS, LF, and Slack times for each activity into columns D

- Enter the "Immediate Predecessors" information into cells B4-B11
- Compute and enter the ES, EF, LS, LF, and Slack times for each activity into columns D through H as indicated
- Answer the following
- How long will the project take? (Enter value)
- What is the critical path?
For the project from the question above, what is the impact on total project duration if Activity C is delayed by 1 period - that is, it took 1 period longer than originally planned? Explain.
For the project from the question above, what is the impact on total project duration if Activity D is shortened by 1 period? Explain.
Project Scheduling Problem Activity On Node Diagram Immediate Predecessors Time (Weeks) 6 ES EF LS LF Activity A Slack B E none B A 3 A 5 D 1 A B,C CE 9 10 E A F H F 14 G D 2. H F,G 7 DStep by Step Solution