Question: An activity on a critical path has an early start time of 20 and a late finish of 30. Which of the following statements is

An activity on a critical path has an early start time of 20 and a late finish of 30. Which of the following statements is true?

A.

The slack time is 10

B.

The early start is 30

C.

The late start is 30

D.

The late start is 20

E.

The early finish is 20