Question: An activity on a critical path has an early start time of 20 and a late finish of 30. Which of the following statements is

 An activity on a critical path has an early start time

An activity on a critical path has an early start time of 20 and a late finish of 30. Which of the following statements is true? A. The early start is 30 OB. The early finish is 20 OC. The late start is 20 D. The slack time is 10 O E. The late start is 30