Question: An activity on a PERT network has the following time estimates: optimistic = 6, most likely = 14, and pessimistic = 26. Its standard deviation
An activity on a PERT network has the following time estimates: optimistic = 6, most likely = 14, and pessimistic = 26. Its standard deviation is (please round off to two decimal digits)