Question: Question 20 (1 point) An activity on a PERT network has the following time estimates: optimistic = 1, most likely = 12, and pessimistic =

Question 20 (1 point) An activity on a PERT

Question 20 (1 point) An activity on a PERT network has the following time estimates: optimistic = 1, most likely = 12, and pessimistic = 29. Its expected time is (please round off to two decimal digits) Your Answer: Your Answer Question 21 (1 point) An activity on a PERT network has the following time estimates: optimistic = 4, most likely = 18, and pessimistic = 22. Its variance is (please round off to two decimal digits) Your Answer: Your Answer Question 22 (1 point) An activity on a PERT network has the following time estimates: optimistic = 4, most likely = 18, and pessimistic = 27. Its standard deviation is (please round off to two decimal digits) = Your

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!