Question: An activity on a PERT network has the following time estimates: optimistic = 5, most likely = 11, and pessimistic = 29. Its expected time

An activity on a PERT network has the following time estimates: optimistic = 5, most likely = 11, and pessimistic = 29. Its expected time is? (two decimal digits)