Question: An activity on a PERT network has the following time estimates: optimistic = 7, most likely = 16, and pessimistic = 28. Its variance is?

An activity on a PERT network has the following time estimates: optimistic = 7, most likely = 16, and pessimistic = 28. Its variance is? (two decimal places)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!