Question: Question 22 (1 point) An activity on a PERT network has the following time estimates: optimistic - 7, most likely = 16, and pessimistic -

Question 22 (1 point) An activity on a PERT
Question 22 (1 point) An activity on a PERT network has the following time estimates: optimistic - 7, most likely = 16, and pessimistic - 23. Its standard deviation is (please round off to two decimal digits) Your Answer: Your