Question: An activity on a PERT network has these time estimates: optimistic.2most likely unknown, and pessimistic - unknown. If variance 2.25 and expected time - 7.5,

An activity on a PERT network has these time estimates: optimistic.2most likely unknown, and pessimistic - unknown. If variance 2.25 and expected time - 7.5, what are the most likely and pessimistic estimates? 8,12 5,12 OB 11 5.11 6.9
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
