Question: An activity on a PERT network has these time estimates: optimistic = 2. most likely = 3, and pessimistic = 10. What is its expected

An activity on a PERT network has these time estimates: optimistic = 2. most likely = 3, and pessimistic = 10. What is its expected activity time and variance
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
